We are pleased to provide an update on the ongoing construction project at SUNCITY CHEMICAL AND MINERALS in Rajasthan, India. A recent site inspection has confirmed significant progress on the Twin Shaft Vertical Kiln Flex Reversy 6, a coal-fired installation designed to enhance our production capabilities.
The kiln shell construction is nearing completion, marking a major milestone in the project. Current efforts are focused on advancing several critical components, including: electrical Control Panel Room, the CIM-FireSolid Combustion System, the Hydraulic Plant, the Blower Room, and the refractories. We are on track for the Quicklime production plants to begin operations by early 2025.